Gondola Point WWPS Overflow Control and System Optimization Study and Improvement
Federal contribution
$114,714
Federal share50%
of $229.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
20172018201920202021
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Quispamsis
- Construction start
- Jun 15, 2017(actual)
- Construction end
- Oct 31, 2020(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end18 months lateforecast Apr 30, 2019
Also in Quispamsis