Jonathan Creek Culvert Replacement
Federal contribution
$1.1M
$1,140,205
Federal share33%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 1, 2015
20162017
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Moncton
- Construction start
- Jun 6, 2016(actual)
- Construction end
- Jun 26, 2017(actual)
Against the original forecast
- Construction start7 months lateforecast Nov 2, 2015
- Construction end7 weeks earlyforecast Aug 15, 2017
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46080 in the federal list. How to read these figures.