Englishman River Water Service (ERWS)
Federal contribution
$3.0M
$3,000,000
Federal share12%
of $24.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2015
20162017201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Parksville
- Construction start
- Mar 15, 2017(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2019
Also in Parksville
- Drinking Water Supply Transmission Mains and Secondary Membrane Water Treatment$3.7M
- Parksville - Moilliet Street Upgrade$872.8K
- Parksville - Improvements to Public Spaces in Parksville Community Park$689.2K
- San Pareil Water System - Treatment Upgrades$387.6K
- Parksville - Springwood Water Supply Complex Upgrade$226.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46101 in the federal list. How to read these figures.