San Pareil Water System - Treatment Upgrades

Parksville, British Columbia

completeDrinking WaterCWWF
Federal contribution
$387,628
Federal share50%

of $775.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Mar 1, 2017(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction start8 months earlyforecast Oct 23, 2017
  • Construction end4 weeks lateforecast Jan 31, 2019

Also in Parksville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47693 in the federal list. How to read these figures.