Pritchard Community Sewer System Solids Management

Thompson-Nicola, British Columbia

completeWastewaterSCF
Federal contribution
$147,131
Federal share33%

of $441.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 10, 2015
20162017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 4, 2016(actual)
Construction end
Dec 23, 2016(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 1, 2016
  • Construction end8 weeks lateforecast Oct 28, 2016