Wastewater Facility Upgrades
Hudson's Hope, British Columbia
Federal contribution
$792,666
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2015
201620172018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- District of Hudson's Hope
- Construction start
- Jun 23, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction end4 weeks lateforecast Feb 28, 2018
Also in Hudson's Hope
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46147 in the federal list. How to read these figures.