Back to projects

BC Hydro Customer Connection Project - Westcoast Energy Inc. - Compressor Station N5

Hudson's Hope, British Columbia

underwayGreen EnergyGIS
Federal contribution
$15.0M
$15,000,000
Federal share50%

of $30.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2025
202420252026
BuiltForecast

Approved 15 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 18, 2025(actual)
Construction end
May 15, 2026(forecast)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 15, 2025

Also in Hudson's Hope

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67905 in the federal list. How to read these figures.