Barnet Highway Landfill Closure
Federal contribution
$705,500
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2015
20162017
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Port Moody
- Construction start
- Feb 27, 2017(actual)
- Construction end
- Sep 15, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast Feb 1, 2017
- Construction end3 months lateforecast Jun 1, 2017
Also in Port Moody
- Port Moody - Recreation Chiller Replacement$868.6K
- Angela Drive & Cecile Drive - Utility & Roadworks Improvements$862.5K
- Port Moody - Noons Creek Bridge Replacement$501.9K
- Port Moody - Inlet Park Sports Field Redevelopment$206.4K
- Update to TransPort Moody (Master Transportation Plan) to match the Climate Action Plan for Port Moody, British Columbia$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46157 in the federal list. How to read these figures.