Barnet Highway Landfill Closure

Port Moody, British Columbia

completeBrownfield Remediation And RedevelopmentSCF
Federal contribution
$705,500
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2015
20162017
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Port Moody
Construction start
Feb 27, 2017(actual)
Construction end
Sep 15, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Feb 1, 2017
  • Construction end3 months lateforecast Jun 1, 2017

Also in Port Moody