Angela Drive & Cecile Drive - Utility & Roadworks Improvements
Federal contribution
$862,500
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Port Moody
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Oct 16, 2017
- Construction end2 weeks lateforecast Mar 15, 2018
Also in Port Moody
- Port Moody - Recreation Chiller Replacement$868.6K
- Barnet Highway Landfill Closure$705.5K
- Port Moody - Noons Creek Bridge Replacement$501.9K
- Port Moody - Inlet Park Sports Field Redevelopment$206.4K
- Update to TransPort Moody (Master Transportation Plan) to match the Climate Action Plan for Port Moody, British Columbia$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49828 in the federal list. How to read these figures.