Prince Rupert Raw Water Supply

Prince Rupert, British Columbia

completeDrinking WaterSCF
Federal contribution
$2.2M
$2,193,028
Federal share33%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2015
201620172018
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Prince Rupert
Construction start
Apr 4, 2017(actual)
Construction end
Jul 18, 2018(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast May 30, 2017
  • Construction end3 months lateforecast Apr 30, 2018