Prince Rupert - Moresby Avenue Wastewater Treatment Facility
Prince Rupert, British Columbia
Federal contribution
$2.2M
$2,198,200
Federal share40%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 12, 2025
today
202420252026
BuiltForecast
Approved 2.4 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Prince Rupert
- Construction start
- Jan 26, 2026(actual)
- Construction end
- Sep 30, 2026(forecast)
Against the original forecast
- Construction start8 weeks lateforecast Dec 1, 2025
Also in Prince Rupert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66777 in the federal list. How to read these figures.