Centre Street Reconstruction

Brockville, Ontario

completeWastewaterSCF
Federal contribution
$348,829
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2015
2016
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Brockville
Construction start
Jul 18, 2016(actual)
Construction end
Nov 19, 2016(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 4, 2016
  • Construction end3 weeks lateforecast Oct 28, 2016