Reconstruction of Elora Street, Harriston from William Street to Town Limits (130m south of Jessie Street)

Minto, Ontario

completeDrinking WaterSCF
Federal contribution
$507,304
Federal share22%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2015
20162017
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Minto
Construction start
May 19, 2015(actual)
Construction end
Jan 31, 2017(actual)

Against the original forecast

  • Construction end5 months lateforecast Aug 31, 2016