Upgrading of Approximately 420m of Sanitary Sewer, Storm-water and Watermain Integral to the George Street Reconstruction

Minto, Ontario

completeWastewaterCWWF
Federal contribution
$445,394
Federal share34%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Minto
Construction start
Jun 9, 2017(actual)
Construction end
Aug 2, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Nov 15, 2016