Schedule
Announced and approvedJun 25, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- County of Northumberland
- Construction start
- Oct 31, 2018(actual)
- Construction end
- Jan 30, 2020(actual)
Against the original forecast
- Construction start10 months lateforecast Jan 1, 2018
- Construction end2 months earlyforecast Mar 31, 2020