Upgrades to Public Drop-Off Areas at Landfill & Transfer Stations

Cobourg, Ontario

completeSolid Waste ManagementSCF
Federal contribution
$150,273
Federal share30%

of $508.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2015
20162017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
County of Northumberland
Construction start
Oct 31, 2018(actual)
Construction end
Jan 30, 2020(actual)

Against the original forecast

  • Construction start10 months lateforecast Jan 1, 2018
  • Construction end2 months earlyforecast Mar 31, 2020

Also in Cobourg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46191 in the federal list. How to read these figures.