Back to projects

London Road Bridge #4003

South Huron, Ontario

completeHighways and RoadsSCF
Federal contribution
$155,732
Federal share33%

of $468.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 4, 2015
2016
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of South Huron
Construction start
Apr 4, 2016(actual)
Construction end
Oct 17, 2016(actual)

Against the original forecast

  • Construction end3 months earlyforecast Jan 31, 2017

Also in South Huron