William Street Sanitary Sewage Pumping Station Upgrades
Federal contribution
$656,286
Federal share35%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018201920202021
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of South Huron
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Dec 31, 2020(actual)
Against the original forecast
- Construction end9 months earlyforecast Sep 30, 2021
Also in South Huron
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48574 in the federal list. How to read these figures.