William Street Sanitary Sewage Pumping Station Upgrades

South Huron, Ontario

completeWastewaterCWWF
Federal contribution
$656,286
Federal share35%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018201920202021
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of South Huron
Construction start
Jun 1, 2017(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction end9 months earlyforecast Sep 30, 2021