Back to projects

Cobden Wastewater Treatment Plant (WWTP) Upgrade

Whitewater Region, Ontario

completeWastewaterSCF
Federal contribution
$3.1M
$3,136,477
Federal share33%

of $9.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2015
2016201820202022
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Oct 8, 2018(actual)
Construction end
Mar 21, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 6, 2018
  • Construction end6 months lateforecast Sep 30, 2021

Also in Whitewater Region

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46204 in the federal list. How to read these figures.