Cobden Wastewater Treatment Plant (WWTP) Upgrade
Federal contribution
$3.1M
$3,136,477
Federal share33%
of $9.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2015
2016201820202022
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Township of Whitewater Region
- Construction start
- Oct 8, 2018(actual)
- Construction end
- Mar 21, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 6, 2018
- Construction end6 months lateforecast Sep 30, 2021
Also in Whitewater Region
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46204 in the federal list. How to read these figures.