Beachburg Arena Restart

Whitewater Region, Ontario

completeRecreationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Oct 13, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 3, 2021

Also in Whitewater Region

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59184 in the federal list. How to read these figures.