Construction of water supply infrastructure
Federal contribution
$1.1M
$1,099,890
Federal share33%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2015
20162017201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Mississaugas of Scugog Island First Nation
- Construction start
- Nov 12, 2018(actual)
- Construction end
- Mar 20, 2020(actual)
Against the original forecast
- Construction end4 months lateforecast Nov 15, 2019
Also in Scugog