Back to projects

Joe Fowler Picnic Shelter Replacement

Scugog, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2023(actual)
Construction end
Nov 2, 2023(actual)

Also in Scugog