Joe Fowler Picnic Shelter Replacement
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the Township of Scugog
- Construction start
- Jun 1, 2023(actual)
- Construction end
- Nov 2, 2023(actual)
Also in Scugog