Town of Penhold Water Reservoir

Penhold, Alberta

completeDrinking WaterSCF
Federal contribution
$1.2M
$1,200,000
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
201620172018
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Penhold
Construction start
Aug 31, 2015(actual)
Construction end
May 30, 2018(actual)

Against the original forecast

  • Construction start2 years earlyforecast Aug 31, 2017
  • Construction end5 months lateforecast Dec 31, 2017

Also in Penhold

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46264 in the federal list. How to read these figures.