Town of Penhold Water Reservoir
Federal contribution
$1.2M
$1,200,000
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Penhold
- Construction start
- Aug 31, 2015(actual)
- Construction end
- May 30, 2018(actual)
Against the original forecast
- Construction start2 years earlyforecast Aug 31, 2017
- Construction end5 months lateforecast Dec 31, 2017
Also in Penhold
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46264 in the federal list. How to read these figures.