Back to projects

Connectivity and expansion of trails, including footbridge, crosswalks, lighting, boat dock and aeration for Penhold, Alberta

Penhold, Alberta

completeActive TransportationATF
Federal contribution
$915,077
Federal share59%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 31, 2023
2023202420252026
Built

Approved 6 weeks before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Penhold
Construction start
Jun 1, 2023(actual)
Construction end
Dec 11, 2025(actual)

Against the original forecast

  • Construction end11 months lateforecast Dec 31, 2024

Also in Penhold