Foothills Millarville Water Supply
Federal contribution
$1.7M
$1,666,650
Federal share33%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipal District of Foothills
- Construction start
- Jan 15, 2016(actual)
- Construction end
- Sep 30, 2020(actual)
Against the original forecast
- Construction start20 months earlyforecast Aug 31, 2017
- Construction end2 weeks earlyforecast Oct 15, 2020
Also in Foothills No. 31
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46293 in the federal list. How to read these figures.