Installation of Solar PV, Energy Efficiency Measures and Combined Heat and Power Systems at the Scott Seaman Sports Rink
Federal contribution
$1.2M
$1,173,377
Federal share73%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 22, 2024
2023202420252026
Built
Approved 20 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Municipal District of Foothills
- Construction start
- Jun 10, 2025(actual)
- Construction end
- Apr 30, 2026(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 1, 2025
- Construction end4 months lateforecast Dec 31, 2025
Also in Foothills No. 31
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65532 in the federal list. How to read these figures.