Whitecap Dakota First Nation Water System Expansion
Whitecap Dakota First Nation, Saskatchewan
Federal contribution
$4.5M
$4,530,000
Federal share33%
of $13.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2016
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Whitecap Dakota First Nation
- Construction start
- Mar 15, 2017(actual)
- Construction end
- Mar 22, 2019(actual)
Against the original forecast
- Construction start2 months earlyforecast May 15, 2017
- Construction end7 weeks lateforecast Jan 31, 2019
Also in Whitecap Dakota First Nation