Whitecap Dakota First Nation Water System Expansion

Whitecap Dakota First Nation, Saskatchewan

completeDrinking WaterNRP
Federal contribution
$4.5M
$4,530,000
Federal share33%

of $13.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 29, 2016
201720182019
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Mar 15, 2017(actual)
Construction end
Mar 22, 2019(actual)

Against the original forecast

  • Construction start2 months earlyforecast May 15, 2017
  • Construction end7 weeks lateforecast Jan 31, 2019

Also in Whitecap Dakota First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46346 in the federal list. How to read these figures.