Whitecap Dakota First Nation Transit Study
Whitecap Dakota First Nation, Saskatchewan
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 10, 2024
20232024
Built
Approved 2 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Whitecap Dakota First Nation
- Construction start
- Jul 25, 2022(actual)
- Construction end
- Mar 27, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast Dec 1, 2021
- Construction end9 months lateforecast Jun 30, 2022
Also in Whitecap Dakota First Nation