Lagoon Storage Cell Expansion
Federal contribution
$531,489
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Indian Head
- Construction start
- Jun 6, 2016(actual)
- Construction end
- Oct 30, 2017(actual)
Against the original forecast
- Construction end17 months earlyforecast Mar 31, 2019
Also in Indian Head
- Town of Indian Head - Detailed Design and Construction of Landfill Closure$997.1K
- Town of Indian Head Swimming Pool Renovation$702.1K
- Indian Head Theatre & Community Arts Inc. - Grand Theatre Interior Renovation Phase 1$548.2K
- Clear Well Reservoir Upgrade - Indian Head$333.3K
- Town of Indian Head - Sunbeam Creek Walking Trail Revitalization$233.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46362 in the federal list. How to read these figures.