Indian Head Theatre & Community Arts Inc. - Grand Theatre Interior Renovation Phase 1
Federal contribution
$548,156
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 14, 2022
today
20232024202520262027
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Indian Head Theatre & Community Arts Inc.
- Construction start
- Mar 2, 2026(forecast)
- Construction end
- Nov 30, 2026(forecast)