Lagoon Expansion

Stoughton, Saskatchewan

completeWastewaterSCF
Federal contribution
$183,333
Federal share33%

of $550.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Stoughton
Construction start
Jul 4, 2016(actual)
Construction end
Nov 8, 2016(actual)

Against the original forecast

  • Construction end8 weeks earlyforecast Dec 31, 2016