Town of Stoughton and RM of Tecumseh No. 65 Main Water Line Replacement and Truck Fill Station
Federal contribution
$1.2M
$1,241,040
Federal share40%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2024
202420252026
BuiltForecast
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Stoughton
- Construction start
- Sep 11, 2024(actual)
- Construction end
- Dec 31, 2025(forecast)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2024
Also in Stoughton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67535 in the federal list. How to read these figures.