Upper Skeena Recreation Centre “Heart of the Hazeltons”

Kitimat-Stikine, British Columbia

completeRecreationMIC
Federal contribution
$1.9M
$1,875,788
Federal share12%

of $15.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 26, 2016
201720182019
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
May 31, 2017(actual)
Construction end
Jan 24, 2019(actual)

Against the original forecast

  • Construction end3 months lateforecast Oct 25, 2018