Upper Skeena Recreation Centre Heart of the Hazeltons
Kitimat-Stikine, British Columbia
Federal contribution
$1.9M
$1,875,788
Federal share12%
of $15.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 26, 2016
201720182019
Built
Approved 8 weeks before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Regional District of Kitimat-Stikine
- Construction start
- May 31, 2017(actual)
- Construction end
- Jan 24, 2019(actual)
Against the original forecast
- Construction end3 months lateforecast Oct 25, 2018