Kitimat-Stikine - Telegraph Creek Boat Launch and Dock
Kitimat-Stikine, British Columbia
Federal contribution
$227,308
Federal share60%
of $378.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022
Built
Approved 6 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Regional District of Kitimat-Stikine
- Construction start
- Dec 1, 2020(actual)
- Construction end
- Dec 14, 2021(actual)
Against the original forecast
- Construction start3 months earlyforecast Mar 15, 2021
- Construction end2 weeks earlyforecast Dec 31, 2021