Nithburg Fibre to the Home
Federal contribution
$135,146
Federal share25%
of $549.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 31, 2015
ApprovedJun 13, 2016
20162017
Built
Approved 10 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Mornington Communications Co-op Ltd.
- Construction start
- Apr 3, 2017(actual)
- Construction end
- Nov 1, 2017(actual)