Replacement of the St. Clements Arena Roof Surface
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Wellesley
- Construction start
- Oct 4, 2021(actual)
- Construction end
- Oct 29, 2021(actual)
Also in Wellesley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59565 in the federal list. How to read these figures.