Musée d'art contemporain de Montréal
Federal contribution
$18.9M
$18,850,000
Federal share50%
of $37.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 13, 2016
today
2016201920222025
BuiltForecast
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Place des Arts of Montreal
- Construction start
- Feb 1, 2024(actual)
- Construction end
- Jan 1, 2027(forecast)
Against the original forecast
- Construction start3 weeks lateforecast Jan 8, 2024
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46443 in the federal list. How to read these figures.