City of Calgary Flood Mitigation

Calgary, Alberta

completeDisaster MitigationNRP
Federal contribution
$10.5M
$10,469,139
Federal share22%

of $46.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 10, 2016
20172019202120232025
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Calgary
Construction start
Aug 15, 2017(actual)
Construction end
Aug 19, 2025(actual)

Against the original forecast

  • Construction start14 months earlyforecast Oct 1, 2018
  • Construction end10 months lateforecast Oct 31, 2024

Also in Calgary