City of Edmonton Stormwater Management - Mill Woods Area

Edmonton, Alberta

underwayDisaster MitigationNRP
Federal contribution
$30.3M
$30,316,000
Federal share33%

of $91.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2016
today
2017202020232026
BuiltForecast

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Edmonton
Construction start
Mar 1, 2017(actual)
Construction end
Dec 31, 2027(forecast)

Against the original forecast

  • Construction start2 weeks earlyforecast Mar 15, 2017

Also in Edmonton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46475 in the federal list. How to read these figures.