Highway 37 - Nass River Bridge Replacement

Stewart, British Columbia

completeHighways and RoadsNRP
Federal contribution
$10.7M
$10,677,500
Federal share45%

of $23.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 24, 2016
201720182019
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
May 22, 2018(actual)
Construction end
Oct 31, 2019(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Apr 30, 2018