Stewart Wastewater Rehabilitation

Stewart, British Columbia

completeWastewaterCWWF
Federal contribution
$560,000
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Stewart
Construction start
Oct 10, 2017(actual)
Construction end
Oct 31, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 15, 2017
  • Construction end5 months earlyforecast Mar 31, 2020