Highway 16 - Bunce Road to Blackwater Road 4-Laning
Prince George, British Columbia
Federal contribution
$8.2M
$8,206,791
Federal share50%
of $16.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 28, 2016
20172018
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of British Columbia
- Construction start
- Mar 1, 2017(actual)
- Construction end
- Oct 10, 2018(actual)
Against the original forecast
- Construction start3 months earlyforecast May 31, 2017
- Construction end3 weeks earlyforecast Oct 31, 2018
Also in Prince George
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46559 in the federal list. How to read these figures.