Highway 16 - Bunce Road to Blackwater Road 4-Laning

Prince George, British Columbia

completeHighways and RoadsNRP
Federal contribution
$8.2M
$8,206,791
Federal share50%

of $16.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 28, 2016
20172018
Built

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Mar 1, 2017(actual)
Construction end
Oct 10, 2018(actual)

Against the original forecast

  • Construction start3 months earlyforecast May 31, 2017
  • Construction end3 weeks earlyforecast Oct 31, 2018

Also in Prince George

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46559 in the federal list. How to read these figures.