Prince George - New Aquatic Centre

Prince George, British Columbia

completeRecreationCCRIS
Federal contribution
$5.5M
$5,454,793
Federal share40%

of $13.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022
Built

Approved 6 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Prince George
Construction start
Jul 29, 2020(actual)
Construction end
Nov 22, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 30, 2020