Regional Lagoon Facility

Frenchman Butte No. 501, Saskatchewan

completeWastewaterNRP
Federal contribution
$4.2M
$4,166,667
Federal share33%

of $12.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 31, 2017
2017201820192020
Built

Approved 8 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Mar 12, 2018(actual)
Construction end
Sep 14, 2020(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2020

Also in Frenchman Butte No. 501

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46572 in the federal list. How to read these figures.