Regional Lagoon Facility
Frenchman Butte No. 501, Saskatchewan
Federal contribution
$4.2M
$4,166,667
Federal share33%
of $12.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 31, 2017
2017201820192020
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Rural Municipality of Frenchman Butte No. 501
- Construction start
- Mar 12, 2018(actual)
- Construction end
- Sep 14, 2020(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 31, 2020
Also in Frenchman Butte No. 501
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46572 in the federal list. How to read these figures.