RM of Frenchman Butte No. 501 - Frenchman Butte Pipestone Creek Culvert Replacement
Frenchman Butte No. 501, Saskatchewan
Federal contribution
$166,700
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2024
202420252026
BuiltForecast
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Frenchman Butte No. 501
- Construction start
- Jul 1, 2025(actual)
- Construction end
- Jun 30, 2026(forecast)
Against the original forecast
- Construction start2 weeks lateforecast Jun 15, 2025