Water & Wastewater Treatment Upgrade
Federal contribution
$2.0M
$2,045,000
Federal share32%
of $6.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 13, 2016
201720182019
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Lanigan
- Construction start
- Apr 30, 2017(actual)
- Construction end
- Apr 2, 2019(actual)
Against the original forecast
- Construction start2 weeks lateforecast Apr 15, 2017
Also in Lanigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46577 in the federal list. How to read these figures.