Town of Lanigan & District Waterpark
Federal contribution
$1.1M
$1,111,700
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
2021202220232024
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Lanigan
- Construction start
- Jun 30, 2022(actual)
- Construction end
- Jan 16, 2024(actual)
Against the original forecast
- Construction end5 months earlyforecast Jun 30, 2024
Also in Lanigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57147 in the federal list. How to read these figures.