Place des Canotiers
Federal contribution
$4.1M
$4,135,193
Federal share45%
of $9.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2016
201720182019
Built
Approved 6 weeks before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Société québécoise des infrastructures (SQI)
- Construction start
- Apr 14, 2016(actual)
- Construction end
- Jan 31, 2019(actual)
Against the original forecast
- Construction end20 months lateforecast May 31, 2017
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46632 in the federal list. How to read these figures.