Back to projects

Expansion and redevelopment of the Centre communautaire des Chutes

Québec, Quebec

completeRecreationLUCC
Federal contribution
$1.5M
$1,460,167
Federal share33%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
201720182019
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Large Urban Centres Component
Ultimate recipient
City of Québec
Construction start
May 3, 2016(actual)
Construction end
Aug 31, 2019(actual)

Against the original forecast

  • Construction start16 months earlyforecast Sep 1, 2017
  • Construction end8 months lateforecast Dec 31, 2018

Also in Québec