Construction of a community centre at Bardy park
Federal contribution
$2.9M
$2,916,881
Federal share33%
of $8.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
201720182019
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Québec
- Construction start
- May 3, 2016(actual)
- Construction end
- Aug 31, 2019(actual)
Against the original forecast
- Construction start16 months earlyforecast Sep 1, 2017
- Construction end8 months lateforecast Dec 31, 2018