Water intake Upgrade

Glovertown, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$112,588
Federal share33%

of $337.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
2017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Glovertown
Construction start
Nov 20, 2016(actual)
Construction end
Sep 1, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast May 15, 2016
  • Construction end2 months earlyforecast Oct 31, 2017

Also in Glovertown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46670 in the federal list. How to read these figures.